Reason? The construction of an pedestrian overpass with a lift.
September 2, 2018 – September 6, 2018 (for 5 days)
(hopefully there will be no delay, it will create a huge mess as you can imagine. Traffic will have to be redirected to some other path!)
Details.
September 2, 2018 at 8.00 am to 6 th September 2018 at 24.00 hrs.
– make permanent road closure The Pattaya Tunnel, Chonburi Road to Sattahip
September 3, 2018 at 8:00 am – 4:00 pm
– Close the road to Sattahip to Chonburi.
On September 6, 2018, at 20.00-22.00 hrs.
– Prepare to install the overpass.
On September 6, 2018 at 22.00-24.00 hrs.
– make permanent road closure From under the 7th bridge, section 5 to the mouth of Soi Siam Country Club.